|
1.02.2015
Within the frames of implementation of object construction by the Customer, «Westport Trading Ltd.» company has concluded Agreement No. 22/12 dated 25.01.2013 with our enterprise for the “Execution of the full scope of construction and installation works including preoperational tests on “Turn key” basis.
The scope of works included the following:
- preliminary technical preparation, elaboration of methods of installation of non-standard equipment with specific conditions
- immediate arrangement and execution of works at Site
- quality control and technology control measures
- preparation, packaging and submission of executive and technical documents
- carrying out laboratory tests
- Site coordination and control of subcontractor
General milestones of object construction
Mobilization, construction of camp and utilities |
April-June 2013 |
Preparatory works at construction site |
May-September 2013 |
Execution of construction works at Site |
November 2013 |
Mechanical and installation works (commencement) |
April 2014 |
Eleectrical equipment installation , instrumentation and heat insulation works |
September 2014 |
Chemical treatment and painting works |
September 2014 |
Mechanical completion of the main works |
November-December 2014 |
Pre-operational tests and setting up works |
December 2014 – January 2015 |
Start-up and adjustment works (commencement) |
February 2015 |
Construction, mechanical and erection and welding works have been carried out by own forces of the enterprise, with involvement of subcontractors in execution of works listed below:
- Electrical installation works
- Instrumentation installation works
- Heat insulation works
Sandblasting treatment and painting of metal structures and pipelines (partial).
The construction was in process on 24-hour rate. The average number of the personnel made up 436 persons and in production peaks (in September-November 2014) the number of the personnel reached 732 persons.
For the period of construction the following was carried out:
Total volume of earth works 31 260.00 m3
Total volume in-situ reinforced concrete structures 9 670.00 m3
Total weight of installed metal structures and equipment 1 882.74 ton,
including:
Installation of heat exchange tanks 21.7 ton
Installation of tansk, receivers and other equipment 362.77 ton
Installation of oxidant and stripping towers, 84.06 ton
coolers, separators and other equipment
Installation of condenser units, vacuum columns, pumps and etc. 24.27 ton
Installation of metal structures (С245, С255, С235) 1 327.01 ton
Installation of steel ladders and maintenance platforms 63.00 ton
There was carried out production of blocks and installation of pipelines of various diameters and steel grades, including carbon and high-carbon steel, including ХМ, НЖ, with appropriate control of welding methods and testing.
Total length of power cables has made up 145 657 km
Electrical heating of pipelines 13.2 km
Equipment installation 2 361 pcs.
Heat insulation of equipment and pipeline surfaces 13 341 m2
Area of painting of steel structures and pipelines
Rust-preventing paint 21 761 m2
Fire-proof paint 28 520 m2
There were no claims or reproof from the Customer’s side upon completion of construction, what allows us to state the high-quality executed works and successful implementation of the project in general.
|
FEBRUARY 2014 |
|
|
|
MARCH 2014 |
|
|
|
|
APRIL 2014 |
|
|
|
JUNE 2014 |
|
|
|
|
JULY 2014 |
|
|
|
SEPTEMBER 2014 |
|
|
|
OKTOBER 2014 |
|
|
|
NOVEMBER 2014 |
|
|
|
DECEMBER 2014 |
|
|
|
JUNUARY 2015 |
|
|
|
|
|
15.12.2014
In accordance with the National Program of the President of Turkmenistan “About the reform of social and living conditions of the population of settlements, towns, villages and district centers”, “Gunortagurnayishgurlushik” IE has concluded the contract with Capital Construction Department of Ahal district for construction of Cultural Center for 500 seats in the town of Anew of Ak Bugday district of Ahal region. On the basis of concluded contract, the construction works have been commenced on 17th January 2014 and completed in December 2014.
On the 15th of December, 2014 on the threshold on national celebration of Neutrality Day the formal opening of the Cultural Center for 500 seats in the town of Anew was held.
The new building fully complies with the up-to-date requirements. All the conditions for increase of the population cultural level and various hobby group activity and for artists are provided herein. A great auditorium for 500 seats, wardrobe and makeup room, library, audio recording studio, two choreographic halls, rehearsal room, chess room, various rooms for the groups and teams, canteen and recreation room are located inside the center.
Fail-safe functioning of new cultural center is provided by the free-running life-support systems. The area around the Cultural center is well-landscaped.
|
01.10.2014
Construction Departments of our company carried out the following works for the last nine months:
1. It was produced 46 000 cub.m of reinforced concrete,
including
constructed buildings
on construction sites of total area by 12 622.81 sq. м::
Recreation centre in Annau c. |
All buildings |
3 783 sq. м |
Bitumen plant in Seyidi oil refinery plant (BP in SORP) |
Operator's room |
560,56 sq. м |
|
Compressor house |
525,76 sq. м |
TKNPZ reconstruction /Turkmenbashy |
Administrative building, operator's room, transformer substation |
2 040,53 sq. м |
|
Administrative building, operator's room, transformer substation |
4 631,17 sq. м |
|
Administrative building |
779,23 sq. м |
ELOU AT-7 in TKNPZ /Turkmenbashy |
Тransformer substation |
302,56 sq. м |
2. There were erected steel constructions in the followingn objects:
- BP in SORP 1 430 Tn
- ELOU AT-7 in TKNPZ 600 Tn
3. Installed equipment in the following objects in terms:
- BP in SORP 468,034 Tn, including commercial furnace of Penzhimmash (3 pcs.)
- ELOU AT-7 in TKNPZ 59,97 Tn, including furnace block FOSTER WHEELER ITALIANA (1 pcs.)
4. It was prodused and assemblled tehnological pipe range in the following objects:
- BP in SORP 75 Tn
- ELOU AT-7 in TKNPZ 99,874 Tn
Our company Construction Departments also carried out work on the following projects during these nine months period:
Construction department CED-1 In Turkmenbashy city on the area of Turkmenbashy Complex of Oil Refinery our company is doing full comlex of civil and erection works by project "Engineering, procurement and construction of fuel oil vacuum distillation unit , light olefine alkylation unit, light gasoline isomerization and light gasoline mixing unit at Turkmenbashy Oil Processing Complex" (TKNPZ reconstruction).
In this project our interprise participates as a subcontractor of «Hyundai Engineering Ltd» korean company.
The works were began last year and are in progress in compliance with prescriptive construction schedule. |
|
|
|
|
|
|
|
|
|
|
The same department CED-1 is doing the full comllex of works by project "Turkmenbashi Oil crude distillation ELOU-АТ-7 installation at TURKMENBASHI COMPLEX OF OIL REFINERIES." where our Customer is representing Dutch company “Alliance Engineering and Construction B.V.”
Construction department CED-3 in Seyidi city. On the area of the Seydi oil refinery (Seidi Oil Refinery) our company is doing full complex of works on the construction of plants for the bitumen production of volume by 37.2 thousand tons per year. Customer of this project is «Westport Trading Europe Limited» company (USA).
Department CA-1 of Ashgabat city is curring out the final stage of construction work by project "Recreation centre for 500 sits on the “turn-key” basis". Here our company is the main contractor of Customer - Ahal province hyakimlik, Annau city, Turkmenistan. Most of the equipment is installed, performed finishing work and landscaping adjacent territory, we are in line with customer requests for the purchase of furniture and related equipment. |